Announcing Granite’s CM/GC Rehabilitation and Construction Project at SFO
Project Timeline:
- Preconstruction: June 2025 through January 2026
- Major Construction: March 2026 through November 2026
The project will rehabilitate Runway 1R-19L and construct Taxiway W between Taxiway A and Taxiway L. It includes upgrades to the hot mix asphalt pavement, lighting infrastructure, drainage, signage, Runway Status Lights (RWLS), sectionals, grooving, and striping. The existing Taxiway F1 will be demolished, and a new Taxiway W will be constructed.
“We are committed to building a lasting collaboration with SFO and all stakeholders to deliver this critical infrastructure efficiently and effectively, while minimizing disruptions for both employees and SFO passengers,” said Granite Vice President of Regional Operations Brent Fogg. “We are honored to partner with the exceptional SFO team to enhance the airfield and uphold SFO’s reputation as the Best Airport in North America.”
Granite will supply asphalt from its Santa Clara Asphalt facility, approximately 185,000 tons of P401 and P403 Mix.
The total anticipated construction value is estimated at
About Granite
Granite is America’s Infrastructure Company™. Incorporated since 1922, Granite (NYSE:GVA) is one of the largest diversified construction and construction materials companies in
View source version on businesswire.com: https://www.businesswire.com/news/home/20250707561163/en/
Granite Contacts
Media
Erin Kuhlman 831-768-4111
Investors
Wenjun Xu - 831-761-7861
Source: Granite