Granite Awarded $50 Million Contract for Tiger Creek Regulator Dam Spillway Replacement
The project, part of PG&E’s Mokelumne River Hydroelectric Project, involves construction of a new spillway that will replace an existing structure at the Tiger Creek Regulator Dam, a slab and buttress dam originally constructed in 1931. The project will enhance long-term dam safety, improve operational reliability, and ensure compliance with updated regulatory and engineering standards.
Granite’s scope of work includes construction of the new spillway crest structure and chute, installation of a temporary cofferdam to allow work to be performed in dry conditions, excavation and rock anchoring, placement of mass and structural concrete, and decommissioning of the existing spillway. The project also includes improvements to site access, including construction of a permanent access road to support ongoing maintenance of the new spillway.
A separate preconstruction contract, completed in 2024 with an approximate value of
“We have a long history of building critical dam projects for many clients in
Construction began in May 2026, with completion anticipated in May 2028.
About Granite
Granite is America’s Infrastructure Company™. Incorporated since 1922, Granite (NYSE:GVA) is one of the largest diversified construction and construction materials companies in the United States as well as a full-suite civil construction provider. Granite’s Code of Conduct and strong Core Values guide the Company and its employees to uphold the highest ethical standards. Granite is an industry leader in safety and an award-winning firm in quality and sustainability. For more information, visit the Granite website, graniteconstruction.com, and connect with Granite onLinkedIn, X, Facebook,andInstagram.
View source version on businesswire.com: https://www.businesswire.com/news/home/20260722592443/en/
Granite Contacts
Media
Erin Kuhlman 831-768-4111
Investors
Wenjun Xu - 831-761-7861
Source: Granite